Rubblizing concrete pavement

Project Profile -       B1441, Weeley Bypass, Essex

                                   300mm thick reinforced, 10.6m wide

                                   5600m² rubblized using the Multi-Head Badger Breaker®

                                   Principal Contractor - May Gurney

                                   Client - Essex County Council

                                   Works commenced 11th October 2004

                                   Contract period - 3 weeks

General condition of carriageway before removal of asphalt.
Reflective cracking identifies failure of concrete and subgrade layers.


MHB Badger Breaker® Rubblizing 1 lane after the removal of asphalt.


Close up of rubblized pavement.


Grid roller reduces surface particle size and compacts rubblized concrete.


Pneumatic tyre roller completes compaction.


Rubblized concrete surface after compaction - ready for asphalt overlay.


Paving operation on rubblized concrete surface.


The Weeley Bypass, paved and open to traffic.


As the leading full package service provider in the UK and Europe for rubblizing and cracking and seating Antigo's experienced staff are always available to provide consultations to clients, engineers and contractors as they plan concrete pavement rehabilitation and reconstruction projects.